Sidney Lanier Middle School

Houston, Texas

Client

Houston Independent School District

Area

175,000 sq.ft.

Total Cost

$6,200,000

Completion Date

05/2002

The main building of this complex originally was opened in 1935 when air conditioning was not common in public schools. Through the years, the school has undergone numerous remodeling and renovations. The latest renovation included architectural, interior, structural, mechanical, electrical, and plumbing enhancements and repairs to bring the complex into compliance with local, state and national building codes, including ADA requirements.
Architectural work included new flooring systems, restroom modifications, office remodeling, laboratory remodeling, lockers, new ceilings, painting, base work, gymnasium floor refinishing/new bleachers and painting. Auditorium remodeling included a new computer-controlled lighting and sound system, and replacement of termite-infested wood molding/trim work. New site-fabricated materials matched the existing profiles and installations. Restrooms were modified to comply with the ADA. The three-story elevator was upgraded to meet code and ADA requirements. Two outdoor student courtyards were upgraded with sloped walkways and seating areas.
The antiquated roof-mounted two-pipe cooling/heating system was replaced with a new four-pipe system. A new 600-ton chiller with an energy-saving ice-storage system was added to the existing 400-ton chiller. A new electrical service was installed to provide more power for computers and laboratory equipment. A new LAN system was installed to connect with the district’s WAN system.

Additional Information

Cost per Sq Ft

$35.86

Featured in

2004 Educational Interiors

Interior category

Interior Renovation

AS&U Design Competitions

The ultimate tribute to education design excellence. If selected for publication, this distinctive...

Have an exceptional project that deserves national recognition? Want to show your best work to the...