Cimarron Middle School, Interior Finish Remodel

Edmond, Oklahoma

Firm

JHBR Architects, Inc.

Client

Edmond Public Schools

Area

76,000 sq.ft.

Total Cost

$1,381,246

Completion Date

09/2004

Cimarron Middle School, built in 1979, had not been updated since the original design. Renovation commenced after the last day of school in the spring of 2004 and was completed less than three months later.
The facelift converted three 1970s common area reading pits into semi-private computer research and training areas, and replaced flooring, lights, ceilings and wall finishes. Restrooms were renovated to feature maintenance-free, accessible lavatories, along with bright, new finishes. Stimulating accent colors were used to highlight circulation and common areas.
The open media center was transformed from a dull, lifeless area into a bright and exciting focal point through the application of suspended, formed plastic sculptural elements, and the redesign of the skylight and ceiling areas.

Additional Information

Cost per Sq Ft

$18.15

Featured in

2005 Educational Interiors

Category

Renovation

Interior category

Interior Renovation

AS&U Design Competitions

The ultimate tribute to education design excellence. If selected for publication, this distinctive...